The first written route preference is scheduled for June 2027, from a study Waller County commissioned.
TxDOT's official answer is that nothing has been decided, and its own documents show that answer holding until late 2029. Waller County hired its own engineering firm in August 2026 to study the route, and that firm's contract calls for a preferred route by June 2027. For anyone buying, selling or holding land in the study area, the county's study is the one to follow.
The Seller's Disclosure Notice
The TREC Seller's Disclosure Notice now in effect is Form 55-1, effective May 28, 2026. It asks about unplatted easements, lawsuits, conservation easements and notices of governmental ordinance violations. A notice is also set out in Texas Property Code §5.008. Confirm how disclosure rules apply to your property with a real estate attorney or other qualified professional.
Five Lines on a Map, Ranked by Nobody
TxDOT lists 36A North as CSJ 0912-00-646. It would be a new 20- to 25-mile highway from I-10 to US 290, with two main lanes each way, intermittent frontage roads, bicycle and pedestrian facilities and right-of-way of varying width. On the TxDOT 36A North project page, the study area runs from the Brazos River on the west to roughly the county line on the east, between US 290 and I-10. Brookshire, Hempstead, Katy, Pattison, Pine Island, Prairie View and Waller are named in or near it.
The alternatives maps show five corridors labeled Alternatives 1 through 5. The map notes that the numbers indicate neither preference nor priority. The map sheets mark FM 359, FM 362, FM 2855, FM 529, FM 3346 and FM 1458, with the Brazos River and Coastal Prairie Conservancy lands for context. TxDOT hasn't published a written description of which roads or landmarks each alternative follows. The maps are the only reference, so look at them parcel by parcel.
Public scoping open houses took place July 14 and 16, 2026, in Brookshire and at the Waller County Fairgrounds in Hempstead, and comments closed July 31. According to Covering Katy, officials reported more than 700 comments on the North section and described the feedback as "not all positive," without giving a percentage either way.
Two Calendars for One Road
On August 19, 2026, Waller County Commissioners Court voted 4–0 to approve an agreement with BGE, Inc. for a "36A Route Feasibility Study," not to exceed $372,198. The contract, attached to the meeting minutes, includes a project schedule. Set that schedule next to TxDOT's final coordination plan, dated August 2026, and the county's milestones come well ahead of TxDOT's:
| Milestone | Whose study | Scheduled |
|---|---|---|
| Route concepts developed | Waller County / BGE | Aug. 24 – Nov. 20, 2026 |
| Alternative comparison matrix | Waller County / BGE | Nov. 23, 2026 – Mar. 5, 2027 |
| Right-of-way requirements | Waller County / BGE | May 17 – June 4, 2027 |
| Engineering Summary Report | Waller County / BGE | May 17 – June 25, 2027 |
| Reasonable-alternatives public meeting | TxDOT | Early 2028 |
| Recommended-alternative public hearing | TxDOT | Early 2029 |
| Final EIS and Record of Decision | TxDOT | Late 2029 |
The two documents also disagree on one date. BGE's schedule shows a TxDOT public meeting on October 29, 2027, and TxDOT's own coordination plan puts the reasonable-alternatives meeting in early 2028. Either way, the county's work is scheduled to finish months before TxDOT shows the public a shorter list.
The first BGE deliverable, the route concepts, is scheduled to be finished by November 20, 2026, about three weeks after this post's publication date.
What the County Study Is Built to Produce
The scope in the BGE contract goes well beyond collecting data. It requires:
- At least three route concepts, defined well enough to locate bridges, right-of-way, relocations, major utility conflicts and connections to cross streets.
- An alternative comparison matrix scored on measures of effectiveness that Waller County agrees to.
- A preferred route selection and geometric layout.
- KMZ or KML files of the alternatives that can be viewed in Google Earth.
- Meetings with TxDOT and with stakeholders such as the Highway 36A Coalition to share evaluation methods and results, as the county directs.
Waller County sets the scoring criteria and directs who receives the results. The contract doesn't say whether the final report will be published. It describes the work as input into TxDOT's process, not a replacement for it. A county-preferred line drawn with right-of-way requirements and relocations is still the most specific view of 36A North that anyone will have before 2028.
The county's priorities are also on the record. Commissioner and Judge-elect Justin Beckendorff told a regional coalition that Waller County wants a role in choosing the route and in limiting the effect on existing property owners, as reported by Covering Katy. "We want to make sure that we're not going to put it right through the middle of a family farm that's been in operation for four generations," he said. In the same report, he stressed that five alternatives were still under consideration and that "Nothing's set in stone."
In practice, "no route selected" will stay true for TxDOT until late 2029. Waller County may have a written preference by mid-2027, and that preference will reflect what the county weighs, which includes long-held working land.
Right-of-Way Acquisition
TxDOT's project development manual says right-of-way is identified during preliminary engineering.
TxDOT's July 2026 exhibit boards list detailed design, right-of-way acquisition and construction as later steps with no year attached, and they state that right-of-way and construction funding has not been identified.
The Texas Attorney General's Landowner's Bill of Rights, revised November 2025, says owners may hire their own appraiser or attorney.
The Fort Bend Half Shows Where This Is Heading
The southern section, 36A South, runs about 41 miles from FM 1994 south of Needville to I-10 in Katy. It started earlier and gives a preview of the North timeline. TxDOT's August 2026 meeting materials narrowed South to three reasonable alternatives, labeled 4, 8A and 9, and the project is still in environmental review. Community Impact reported that Alternatives 4 and 8A are new corridors, that Alternative 9 would be elevated over existing SH 36 or Spur 10, that a final route is expected by summer 2028 and that construction is projected for 2037, a date that could still move.
The South comments were sharper. Covering Katy reported that a Jacobs representative counted more than 900 comments after the Katy and Rosenberg meetings and estimated about 90 percent opposed the project. That figure applies to South only. If North follows the same pattern, the step from five alternatives to a short list is when the comment record and the county's preference will matter most.
Quick Answers
Is any property in Waller County confirmed to be on the 36A route? No. TxDOT has five unranked alternatives and no selected route. Its final route decision is scheduled for late 2029.
Where can I see whether a specific tract falls near an alternative? Use TxDOT's 36A North alternatives maps, which show all five corridors along with the farm-to-market roads they come near.
Will the county's BGE study results be public? The contract requires BGE to share methods and results with TxDOT and stakeholder groups as the county directs. It doesn't address general public release. Watch the Waller County Commissioners Court agendas.
Is the comment period still open? The North scoping comment period closed July 31, 2026. TxDOT's next scheduled North public meeting is the reasonable-alternatives meeting in early 2028.
This post is general information about public documents. It is not legal, tax or financial advice, so confirm how disclosure rules or right-of-way procedures apply to your property with a real estate attorney or other qualified professional.
If you own or are considering acreage between I-10 and US 290, the 36A maps should be part of your valuation and your due diligence. Coldwell Banker Properties Unlimited follows the county study and TxDOT's schedule as part of our land work in Waller County. Ask us for a free property valuation that factors in where your tract sits relative to the study area.